Some pictures to share!!! I really appreciate what developer had done for GALAXY. As you can see, the guard house is attached with washroom, our guards had no excuse to leave the place as i knew from other condominium or gated community, the guards normally used this as an excuse and gone missing for some time.
Besides that, our landscape/garden is definitely safe for children as i can see they took out the stone before filling up with soil. None of the developer will be doing this but Gemitra is the only one that i found!!!
So, let us work hard together to extend the hard work put in by developer. I hope that owners can be part of the volunteer committee members to serve our place better.
HOME SWEET HOME -->
Monday, April 20, 2009
Latest site report. 18th April 2009
On my last visit to the site, Saturday 18th 2009, the work progress is as below. I apologize for not being able to take any photo during my visit there..
1. Road works. - In progress. They are leveling the ground works and adding those loose pebbles and compacting it. Tarmac & Bitumen is expected to be laid maybe early May or end of April.
2. The Wall (Behind Block F). - Almost completed. The wall is high and the metal grille on top of the wall installed. Some wiring is visible along the wall and I assume it is for the CCTV and Lighting.
3. The Playground. - Ground leveling in progress.
4. Block E. - Block E is seems to be completed and we saw them doing the internal cleaning (such as mopping the floor) and throwing the rubbish out from the unit.
5. Block F. - It seems that Block F may still have some internal & external works. Cleaning have not taken place yet. However, the flooring seems to be completed.
6. The Guard House. - Structure seems to be completed. May have some internal works in progress.
Again, I apologize as there is no photo included in this site report and I hope is any of you guys have possession of the latest photo, and want to share it here.. please forward so we can post it here.
1. Road works. - In progress. They are leveling the ground works and adding those loose pebbles and compacting it. Tarmac & Bitumen is expected to be laid maybe early May or end of April.
2. The Wall (Behind Block F). - Almost completed. The wall is high and the metal grille on top of the wall installed. Some wiring is visible along the wall and I assume it is for the CCTV and Lighting.
3. The Playground. - Ground leveling in progress.
4. Block E. - Block E is seems to be completed and we saw them doing the internal cleaning (such as mopping the floor) and throwing the rubbish out from the unit.
5. Block F. - It seems that Block F may still have some internal & external works. Cleaning have not taken place yet. However, the flooring seems to be completed.
6. The Guard House. - Structure seems to be completed. May have some internal works in progress.